A switchboard upgrade is required when the existing switchboard does not meet the standards and requirements necessary to safely connect a solar inverter or battery system. Common reasons include: No RCDs (Residual Current Devices) on the existing switchboard: Australian wiring rules (AS/NZS 3000) require that all new circuits, including solar inverter and battery circuits, are protected by RCDs. Older switchboards may only have circuit breakers (MCBs) without RCD protection. Adding solar or a battery requires either an RCD to be fitted to the new circuit or, if the board cannot accommodate one, a switchboard upgrade. Ceramic fuses (pre-1980s switchboards): Old-style ceramic fuse boards (with rewireable fuses rather than circuit breakers) cannot safely accommodate a solar or battery circuit. A full switchboard upgrade is required before installation can proceed. No spare circuit breaker slots: A solar inverter requires a dedicated circuit breaker. A battery may require a separate breaker. If the existing board is fully occupied: a larger board (or a sub-board) is required. Insufficient busbar rating or old wiring: Very old switchboards may have busbars rated for lower current than modern loads. An electrician's assessment determines whether the existing board can safely accommodate additional load. Main switch is not a combined RCD/switch: In some configurations, the installation standard requires the main switch to incorporate RCD protection. Older boards may not have this.
What a Switchboard Upgrade Involves
A switchboard upgrade is electrical work performed by a licensed electrician. It typically involves:
- Removing the existing meter board, fuse board, or switchboard enclosure
- Installing a new enclosure with a compliant main switch and RCDs
- Transferring existing circuits to the new board
- Adding the new solar inverter circuit (and battery circuit if applicable)
- Issuing a Certificate of Electrical Safety (signed off with Energy Safe Victoria)
The upgrade is coordinated with your DNSP for meter access if required.
Duration: typically half a day to a full day. Power to the property is off during the work.
Who Decides if an Upgrade Is Needed
The decision is made by the licensed electrician who assesses your existing switchboard before installation. AEU’s installation team assesses the switchboard as part of the site assessment process.
Not every installation requires a switchboard upgrade. If your switchboard is a modern RCD-equipped board with available slots: no upgrade is needed and the solar circuit is simply added.
Cost of a Switchboard Upgrade
AEU does not provide a fixed price for switchboard upgrades here as the cost varies based on the existing board condition, the number of circuits, and access. The cost is quoted after site assessment.
A switchboard upgrade is required before installation can proceed safely and legally. It is not an optional add-on.
Common Questions
Can the switchboard be upgraded at the same time as the solar installation? Yes. AEU coordinates the electrical work so both are done together, minimising disruption.
What about the electricity meter? The electricity meter is owned and maintained by your DNSP, not by you or AEU. If a smart (bi-directional) meter is required (it is for solar systems): the DNSP arranges the meter exchange after the installation is complete. This is a separate process from the switchboard upgrade.
Do I need to be home during the switchboard upgrade? Yes. Power will be off during the work. You should plan for a full day without mains power.
When to Call AEU
Call AEU on 1300 996 917 if:
- You are considering solar or battery and want a site assessment including switchboard evaluation
- You have been quoted for a switchboard upgrade and want to understand what is included
- You are adding a second battery or upgrading an inverter and want to know if any switchboard work is needed
- Your switchboard is an older fuse board or ceramic-fuse style and you want it assessed